The third package of the Nagdhunga–Mugling road expansion project, covering the Malekhu–Mugling section of the Prithvi Highway, remains significantly behind schedule, with only around 48 percent of physical progress achieved despite the contract deadline having expired a year ago.
The contract was awarded on December 15, 2022 (Poush 15, 2079 BS), with completion scheduled within three years. However, the project has